This file examines the state of water services in Hadramout Governorate and the challenges associated with weak supplies, outages and water-resource shortages, as well as faults in wells and networks and improvement and expansion projects. It documents the major events, decisions and measures that have affected residents’ access to drinking water in the districts of the coast, valley and desert.

6events
2Year (2023–2024)
0articles
0Document
0photos

Latest events

Project Verified

A one-megawatt solar power station enters the final preparations phase to operate Falak Water Field in Mukalla

On August 19, 2024, the solar power station project designated to operate the Falak well field in Mukalla reached the final preparations stage, with a production capacity of one megawatt and funding from the local authority in Hadramout Governorate. The project aimed to reduce reliance on conventional electricity and diesel fuel, and to strengthen the stability of operations at one of the city’s largest drinking-water sources, which, according to data announced at the time, comprised 16 wells with a production capacity of up to 640 cubic meters per hour.

Al Mukalla City
Crisis Verified

Hadramout floods knock Thillah water wells out of service and damage the Qussay'ar network

Heavy rain and floods in Hadramout Governorate on Wednesday, April 17, 2024, disrupted water supplies from wells in the Thillah area that serve Mukalla, and damaged the water network in Qussay'ar in the eastern part of the governorate. The damage was among the effects of a weather system that hit wide areas of Hadramout, causing losses to infrastructure, electricity networks and roads, and exposing water facilities to the risks of natural disasters.

Al Mukalla City
Crisis Verified

The Al-Naq'ah water line goes out of service, cutting supplies to large parts of Mukalla

On September 24, 2023, the city of Mukalla in Hadramout Governorate experienced a widespread interruption in drinking water supplies after a break in the main line carrying water from the Al-Naq'ah wells took it out of service. Several residential neighborhoods were affected, including Buwaysh, Rawkab, Khalaf, Al-Mihdhar, جول Masah and Al-Dis. The local water and sanitation corporation mobilized its technical teams to repair the line and restore pumping, after maintenance work continued for a second consecutive day.

Al Mukalla City
Crisis Verified

Falk and Thullah Fields Go Out of Service, Worsening Mukalla’s Drinking Water Crisis After Thunderstorms

Mukalla, in Hadramout Governorate, experienced disruptions to its drinking water supply in late August 2023 after technical damage affected the Falk and Thullah fields as a result of storms and thunderstorms. Falk Field was shut down for more than 13 hours, while Thullah Field was temporarily taken out of service. The local authority approved emergency measures to operate the water fields using generators around the clock and provide additional quantities of diesel, in an effort to restore regular pumping to the affected neighborhoods.

Al Mukalla City

About this file

Water is one of the key service and environmental issues in Hadramout, where large areas of the governorate rely on groundwater to meet the needs of residents and agricultural activities, amid challenges related to water-resource management, rising demand for water and infrastructure development.

In recent years, some areas of the governorate have experienced repeated disruptions to drinking-water supplies due to faults in wells, pumps and transmission lines, problems associated with the energy needed to operate them, as well as challenges related to urban expansion and rising maintenance and operating costs.

In Wadi Hadramout, the need to strengthen the capacity of water fields, reservoirs and transmission lines has become apparent, particularly in Seiyun and its outskirts. In early 2023, trial pumping was launched at a new reservoir with a capacity of four thousand cubic meters in Seiyun, as part of projects aimed at supporting supplies. However, subsequent technical faults at the Jathmah water field in June of the same year affected water access in some areas.

On the Hadramout coast, neighborhoods in Mukalla suffered outages and weak water access, including an outage linked to a fault in the transmission line in July 2023, and complaints that supplies were not reaching neighborhoods in the Fuwah area in March 2024.

The challenges also extended to protecting drinking-water sources from encroachments. A field inspection at the Jathmah water field in Seiyun in October 2026 revealed damage linked to encroachments and illegal interventions, amid calls to enforce judicial rulings concerning the protection of the field.

In light of these developments, the file documents the course of the water crisis in Hadramout, from faults, outages and residents’ complaints to remediation and expansion projects and source protection, while tracking what has actually been accomplished and the extent to which it has affected the regularity of the service, rather than relying solely on official announcements and commitments.

Timeline 6 documented events

Loading events…

20234 events
January
Opening Verified

Seiyun Inaugurates 4,000-Cubic-Meter Water Reservoir to Meet Rising Demand

The city of Seiyun in Wadi Hadramout witnessed the launch of trial pumping and the provisional handover of a new water reservoir with a capacity of 4,000 cubic meters on January 2, 2023, along with transmission lines connected to the Jathmah field. The project cost $681,725 and was funded from the oil sales allocation earmarked for the local authority in Wadi and Desert Hadramout. The project was intended to boost storage capacity and improve water distribution amid rising residents’ needs and urban expansion.

Sayun
August
Opening Verified

Continuous Electricity Line Commissioned for Zaman Water Field in Mukalla to Strengthen Supplies to Western Neighborhoods

Mukalla, in Hadramout Governorate, witnessed the commissioning on Tuesday, August 8, 2023, of a continuous electricity line to power the wells of the Wadi Zaman water field, with the aim of reducing the impact of power outages on pumping operations and improving supplies to the Fuwa area and the city’s western neighborhoods. This coincided with continued work on a 12-kilometer water transmission line, with about one kilometer remaining for completion, as part of efforts to address inadequate water access for residents.

Al Mukalla City
Crisis Verified

Falk and Thullah Fields Go Out of Service, Worsening Mukalla’s Drinking Water Crisis After Thunderstorms

Mukalla, in Hadramout Governorate, experienced disruptions to its drinking water supply in late August 2023 after technical damage affected the Falk and Thullah fields as a result of storms and thunderstorms. Falk Field was shut down for more than 13 hours, while Thullah Field was temporarily taken out of service. The local authority approved emergency measures to operate the water fields using generators around the clock and provide additional quantities of diesel, in an effort to restore regular pumping to the affected neighborhoods.

Al Mukalla City
September
Crisis Verified

The Al-Naq'ah water line goes out of service, cutting supplies to large parts of Mukalla

On September 24, 2023, the city of Mukalla in Hadramout Governorate experienced a widespread interruption in drinking water supplies after a break in the main line carrying water from the Al-Naq'ah wells took it out of service. Several residential neighborhoods were affected, including Buwaysh, Rawkab, Khalaf, Al-Mihdhar, جول Masah and Al-Dis. The local water and sanitation corporation mobilized its technical teams to repair the line and restore pumping, after maintenance work continued for a second consecutive day.

Al Mukalla City

No documented events in this period

Figures and statistics

Documented events
6
Time span
2023 – 2024
Articles
0
Documents and photos
0 / 0
20232024

Contact Alhadarmia News Agency

Do you have news, a photo or information from your area? Message us directly at 775925520

Contact us on WhatsApp